Commercial building given a new face lift with new metal cladding

Home / Project / Commercial building given a new face lift with new metal cladding
ABOUT PROJECT

3rd party Engineering was retained to verify the integrity of the building prior to the new construction.

Scope of Work;

  • Supply and installation of 1 – ½’’ Z-bar strapped horizontally 48’’ OC around building
  • Supply and install 1-1/2” Rigid Insulation (5120 sq/ft)
  • Supply and installation of 26Ga. Metal siding, which will run vertically (5,200sq.ft); standard colour and standard paint finish
  • Supply and installation of 26Ga. Metal flashings including ridge cap

What a great new look to an older building, increasing it’s energy efficiency with new insulation under the metal cladding. Great job Cavalry crew!!

PROJECT GALLERY
PROJECT DESCRIPTION
  • Project Type Interior Exterior Finishes
  • Industry Type Commercial
  • Sub-Type Warehousing & Equipment
  • Location Orangeville, Ontario
  • Square ft 6000 sq/ft.
  • Duration 3 weeks

  • -